Time for completion where no date is fixed

It will be observed that the contract which the parties entered into did not fix a date by which the work should be completed. It must, therefore, be assumed that the parties agreed that it should be completed within a reasonable time from the commencement of the work provided the various payments at the stated periods were made regularly as and when demanded, evidence of which should have been adduced at the trial.

BANSON v. ABBEY [1962] 1 GLR 213 [1962] SLR (SC) 12 · Supreme Court · 1962 · KORSAH CJ