[2013] SLR (SC) 25Supreme Court - Ghana2013 SC - GHANA

NDEBUGRE (NO 1) vs. ATTORNEY-GENERAL, AKER ASA & CHEMU POWER CO LTD (NO 1) CIVIL MOTION NO. J1/5/2013 [2013-2014] 2 SCGLR 1134

21 November 2013 · AKAMBA JSC · ≈ 8 min read

Cite as[2013] SLR (SC) 25
Other citation styles and permanent link
OSCOLANDEBUGRE (NO 1) v ATTORNEY-GENERAL, AKER ASA & CHEMU POWER CO LTD (NO 1) [2013] SLR (SC) 25
APANDEBUGRE (NO 1) v ATTORNEY-GENERAL, AKER ASA & CHEMU POWER CO LTD (NO 1), [2013] SLR (SC) 25 (Ghana).
BluebookNDEBUGRE (NO 1) v ATTORNEY-GENERAL, AKER ASA & CHEMU POWER CO LTD (NO 1), [2013] SLR (SC) 25 (Ghana Sup. Ct. 2013).

SLR is the Superlaw Reports citation series assigned by SuperLawGH. It is not an official law report. Suggested styles are a guide, so check your institution’s style guide.

AKAMBA JSC:

(Sitting as a single Justice of the Supreme Court)

Practice and procedure – Interlocutory injunction – Grant – Conditions – Discretionary remedy – Basic principles for grant of interlocutory injunction – Companies Act, 1963 (Act 179) – Petroleum (Exploration and Production) Act, 1984 (PNDCL 84), s 23(15) – High Court (Civil Procedure) Rules, 2004 (CJ 47), Order 25, r 1(1).

It is provided by articles 268 of the 1'992 Constitution that:

"268. Parliamentary ratification of agreements relating to natural resources.

(1) Any transaction, contract or undertaking involving the grant of a right or concession by or on behalf of any person including the Government of Ghana, to any other person or body of persons howsoever described, for the exp loi – tation of any mineral, water or other natural resource of Ghana made or entered into after the coming into force of this Constitution shall be subject to ratification by Parliament.

(2) Parliament may, by resolution supported by the votes of not less than two -thirds of all the members of Parliament, exempt from the provisions of clause (1) of this article any particular class of transactions, contracts or undertakings."

It is also provided by section 23(15) of the Petroleum (Exploration and Production) Act, 1984 (PNDCL 84), that:

"23. Obligations of contractors

( 15) Except for the subcontractors exempted from the requirements of this subsection by the Regulations, a contractor or subcontractor which is not an incorporated company in the Republic under the Companies Act, 1963 (Act 179) shall (a) register an incorporated company in the Republic under the provisions of the Companies Act, 1963 (Act 179), to be authorised to only conduct petroleum operations in respect of which a petroleum agreement or petroleum subcontract has been entered into under this Act and the company shall be a signatory to a petroleum agreement;

(b) maintain an office or establishment in the Republic to carry out petroleum operations and shall have in charge of the office or establishment a representative with full authority to act and to enter into binding commitments on be half of the contractor or subcontractor; and (c) in respect of the petroleum operations, open and maintain an account with a bank in the Republic."

It is further provided by rule 22 of the Supreme Court Rules, 1996 (CI 16), that:

"22. Interlocutory judgment does not prejudice appeal

An interlocutory judgment, decree or order from which there has not been an appeal shall not operate to bar or prejudice the Court from giving its own decision on the appeal that the Court considers just."

It is also provided by Order 25, r 1(1) of the High Court (Civil Procedure) Rules, 2004 (CI 47), that:

"Order 25, r 1(1): The Court may grant an injunction by an interlocutory order in all cases in which it appears to the Court to be just or convenient to do so, and the order may be made either unconditionally or upon such terms and conditions as the Court considers just."

Held, refusing the application for an injunction: interlocutory injunction is a discretionary remedy and as provided under Order 25, r 1(1) of the High Court (Civil Procedure) Rules, 2004 (CI 47), it may be granted unconditionally or upon such terms and conditions as the court shall think just or convenient so to do. And it is a basic principle of injunction law that, prima facie, a court will not grant an injunction to restrain an actionable wrong for which damages are the proper remedy. Also a prima facie case for an injunction must be made out before leave is granted and the claim must be made in good faith. Furthermore an injunction will only be granted at the suit of a party having sufficient interest in the relief sought. In determining whether or not to grant an injunction, the court is obliged to consider the comparative convenience, that is to say, it is granted or refused according to the side to which the balance of convenience is inclined. In the instant case, having considered the averments filed by the parties in support and against the grant of the application, the court is of the view that no prima facie case has been made to warrant the grant of an order of injunction against at the Minister of Energy. Maxwell v Hogg (1867) 2 Ch App 307 at 311 cited.

Per curiam: The record before this court does not demonstrate that the trial of this matter is imminent. The records rather show that the second defendant-respondent AKER ASA, which is at the centre of the whole dispute, is yet to be served with notice of this suit out of jurisdiction, pursuant to leave granted by this court, which is an indication that same has not been registered as a corresponding company under the Companies Act, 1963 (Act 179), as prescribed under section 23(15) of the Petroleum (Exploration and Production) Act, 1984 (PNDCL 84).

Case referred to:

(1) Maxwell v Hogg (1867) 2 Ch App 307.

APPLICATION by the plaintiff-applicant J A Ndebugre for an order of injunction to be issued against the Minister of Energy to prevent the Minister from laying before Parliament as required by article 268 of the 1992 Constitution, an agreement between the Government of Ghana and AGM Petroleum (Gh) Ltd, after the abrogation of the contract between the Government of Ghana and the second defendant-respondent AKER ASA and the third defendant-respo nd – ent Chemu Power Co Ltd, for n on-compliance with section 23(15) of the Petroleum (Exploration and Production) Act, 1984 (PNDCL 84 ).

Th addeus Sory (with him Akua Wirekowaa K odua) for the applicant. Grace Oppong, Senior State Attorney (with her Gyanfua Boakye, Assistant State Attorney) for the first respondent.

Dr Kweku Ainuson for the third respondent.

AKAMBA JSC:

(Sitting as a single Justice of the Supreme Court)

This is an application for an order of interlocutory injunction at the instance of the plaintiff-applicant John Akparibo Ndebugre (hereinafter simply referred to as the plaintiff), for reasons stated in the supporting affidavit filed on 11 October 2013. The first defendant-respondent Attorney- General (hereinafter simply referred to as the first defendant), upon receipt of the motion paper and supporting affidavit, responded in an affidavit dated 7 November 2013, opposing the grant. The applicant prays this court to grant an order of injunction against the Minister for Energy to prevent him from laying before Parliament an agreement between the Government of Ghana and AGM Petroleum (Gh) Ltd, entered after the abrogation of the contract between the Government of Ghana and the second defendant-respondent AKER ASA and third defendant-respondent Chemu Power Co Ltd, for non compliance with section 23(15) of Petroleum (Exploration and Production) Act, 1984 (PNDCL 84). The applicant premises his prayer on his contention that once Parliament has ratified under article 268 of the 1992 Constitution, an agreement entered between the Government of Ghana and another person, the agreement assumes the status of an agreement with the force and backing of the Constitution for which reason such contract cannot be abrogated simply by a decision of a Minister of State. The applicant also bemoans the payment of money to one of the defendants-respondents, ie the second defendant-respondent AKER ASA following upon the alleged void contract.

The first defendant Attorney-General deposed that there was no credence in the applicant's claim that once Parliament had ratified an agreement, that agreement could only be terminated by a judicial declaration or parliamentary resolution. The first defendant contends that the Minister for Energy has the authority to terminate the petroleum agreement without recourse to either the court or Parliament, quoting the same article 268 of the 1992 Constitution also relied upon by the applicant. The first defendant explained that the sum of US $29 million paid to the second defendant was in return for data obtained by the State which payment was not affected by the illegality of the contract.

Interlocutory injunction is a discretionary remedy that a court"may grant if it thinks it just or convenient so to do. It may be granted unconditionally or upon such terms and conditions as the court shall think just. Order 25, r 1(1) of the High Court (Civil Procedure) Rules, 2004 (CI 47), provides that:

"The Court may grant an injunction by an interlocutory order in all cases in which it appears to the Court to be just or convenient so to do, and the order may be made either unconditionally or upon such terms and conditions as the Court considers just."

Rule 22 of the Supreme Court Rules, 1996 (CI 16), also provides that:

"22. Interlocutory judgment does not prejudice appeal

An interlocutory judgment, decree or order from which there has been no appeal shall not operate to bar or prejudice the court from giving its own decision on the appeal that the Court considers just."

It is a basic principle of injunction law that, prima facie, a court will not grant an injunction to restrain an actionable wrong for which damages are the proper remedy. Also a prima facie case for an injunction must be made out before leave is granted and the claim must be made in good faith. Furthermore an injunction will only be granted at the suit of a party having sufficient interest in the relief sought: see Maxwell v Hogg (1867) 2 Ch App 307 at 311. In determining whether or not to grant an injunction, the court is obliged to consider the comparative convenience, that is to say, it is granted or refused according to the side to which the balance of convenience is inclined.

Having therefore considered the averments filed in support and against the grant of this application, it is the view of this court that no prima facie case has been made to warrant the grant of the relief prayed. The record before this court does not demonstrate that the trial of this matter is imminent. The records rather show that the second defendant-respondent AKER ASA, which is at the centre of the whole dispute, is yet to be served with notice of this suit out of jurisdiction, pursuant to leave granted by this court, which is an indication that same has not been registered as a corresponding company under the Companies Act, 1963 (Act 179), as prescribed under section 23(15) of the Petroleum (Exploration and Production) Act, 1984 (PNDCL 84).

In the result, the application is refused.